Broomfield is getting a NEW Community Center!

A full reconstruction of the Broomfield Community Center began in September 2018.

The new facility is anticipated to open Summer 2020.

With such deep roots in the community, your input, feedback, thoughts and feelings about this project are paramount! Take a moment to share your fond memories, what you're excited about with a new facility and ask your questions using the tools below.


Use the Sign Up to Speak Up button on the right for monthly email updates and check out the project timeline and prior community feedback below that. Thank you for joining us on this exciting journey towards a newer, better community center!


Tell us what you think below! (You will need to sign up for a Broomfield Voice account)

A full reconstruction of the Broomfield Community Center began in September 2018.

The new facility is anticipated to open Summer 2020.

With such deep roots in the community, your input, feedback, thoughts and feelings about this project are paramount! Take a moment to share your fond memories, what you're excited about with a new facility and ask your questions using the tools below.


Use the Sign Up to Speak Up button on the right for monthly email updates and check out the project timeline and prior community feedback below that. Thank you for joining us on this exciting journey towards a newer, better community center!


Tell us what you think below! (You will need to sign up for a Broomfield Voice account)

  • News & Updates

    9 months ago
    Bcc april 2019


    The precast structure is substantially complete!



    April 4, 2019 Update:

    At the Bay parking lot the demolition, soil conditioning, and underground utilities are complete. Curb and gutter work and concrete paving is nearing completion, and the asphalt paving scope has started, with the first lift of asphalt schedule to start by April 4th. Weather has had a significant impact on the completion of the parking lot; however, recent weather has provided a good window for completing the asphalt. The anticipated completion of The Bay parking lot is now late-April.

    For the new Community Center, the first phase of site work, to include ditch realignment and north trail reconfiguration, is nearing completion. Weather has also impacted the first phase of site work and completion is now anticipated to be complete mid-April. For the building structure, the building pad preparation and drilled piers are complete. The foundations for the north half of the new building are nearing completion, and the precast structure started erection on February 13th and is anticipated to be completed on schedule, April 5th. Foundation work will be complete by April 9th and Roofing work for the recreational side of the building by the end of April.

    The completion schedule for the new facility anticipates opening in phases with the south half of the facility, including administration offices, meeting rooms and Senior Services, opening in June of 2020 and the remaining facility, demolition of the existing Senior Center, and the remaining site work completing at the end of summer 2020.


    BACKGROUND:

    Adolfson & Peterson Construction (AP) was awarded the Construction Manager/General Contractor (CM/GC) agreement by Council on January 23, 2018, authorizing the contractor to begin the preconstruction services to include constructability reviews and cost estimating to keep the project within budget. Davis has completed the Schematic Design (SD) design stage and is moving into the Design Development (DD) stage. The Concept Review for the Site Development Plan amendment was approved by Council at the April 3, 2018 Council Study Session with several comments. At the May 29, 2018 Council Study Session, the project team presented the current design of the project which was 96,088 square feet and a total project cost of $47.2 million. Council agreed to move forward with Design Development phase for the fully programmed facility as presented. The Site Development Plan (SDP) amendment was brought to the Planning & Zoning Commission on August 13th. The SDP amendment and an amendment to the CM/GC agreement with AP to add the construction scope with a Guaranteed Maximum Price (GMP) was brought to Council and approved on August 28, 2018. The start of the first phase of construction is anticipated to be the beginning of September.

    On July 11, 2017, Council approved a consultant design award to Davis Partnership PC Architects (Davis). Design investigation, research, and public input process have been completed. With the guidance provided by the Stakeholder Committee (composed of representatives from PRAC, HHSAC, and the Senior Resource Board) and the numerous public comments received, Council authorized Staff to proceed with design based upon the 2-story conceptual design at the December 12, 2017, Council Study Session.

    On May 23, 2017, Council authorized staff to pursue debt financing for a new Community Center. The project will construct a new two-story facility and will be phased such that the north wing of the facility (recreational area) will be demolished to allow space on the site for the new facility to be constructed, and allow the south wing (senior services area) of the building to remain open during construction. This phased method will require that some programs move to the Paul Derda Recreation Center while others would be suspended while the new facility is being constructed.

    At the end of August 2018, Staff and Citizens participated in "BCC Demo Day 2018" to say THANK YOU and GOODBYE to our beloved BCC.


    The precast structure is substantially complete!



    April 4, 2019 Update:

    At the Bay parking lot the demolition, soil conditioning, and underground utilities are complete. Curb and gutter work and concrete paving is nearing completion, and the asphalt paving scope has started, with the first lift of asphalt schedule to start by April 4th. Weather has had a significant impact on the completion of the parking lot; however, recent weather has provided a good window for completing the asphalt. The anticipated completion of The Bay parking lot is now late-April.

    For the new Community Center, the first phase of site work, to include ditch realignment and north trail reconfiguration, is nearing completion. Weather has also impacted the first phase of site work and completion is now anticipated to be complete mid-April. For the building structure, the building pad preparation and drilled piers are complete. The foundations for the north half of the new building are nearing completion, and the precast structure started erection on February 13th and is anticipated to be completed on schedule, April 5th. Foundation work will be complete by April 9th and Roofing work for the recreational side of the building by the end of April.

    The completion schedule for the new facility anticipates opening in phases with the south half of the facility, including administration offices, meeting rooms and Senior Services, opening in June of 2020 and the remaining facility, demolition of the existing Senior Center, and the remaining site work completing at the end of summer 2020.


    BACKGROUND:

    Adolfson & Peterson Construction (AP) was awarded the Construction Manager/General Contractor (CM/GC) agreement by Council on January 23, 2018, authorizing the contractor to begin the preconstruction services to include constructability reviews and cost estimating to keep the project within budget. Davis has completed the Schematic Design (SD) design stage and is moving into the Design Development (DD) stage. The Concept Review for the Site Development Plan amendment was approved by Council at the April 3, 2018 Council Study Session with several comments. At the May 29, 2018 Council Study Session, the project team presented the current design of the project which was 96,088 square feet and a total project cost of $47.2 million. Council agreed to move forward with Design Development phase for the fully programmed facility as presented. The Site Development Plan (SDP) amendment was brought to the Planning & Zoning Commission on August 13th. The SDP amendment and an amendment to the CM/GC agreement with AP to add the construction scope with a Guaranteed Maximum Price (GMP) was brought to Council and approved on August 28, 2018. The start of the first phase of construction is anticipated to be the beginning of September.

    On July 11, 2017, Council approved a consultant design award to Davis Partnership PC Architects (Davis). Design investigation, research, and public input process have been completed. With the guidance provided by the Stakeholder Committee (composed of representatives from PRAC, HHSAC, and the Senior Resource Board) and the numerous public comments received, Council authorized Staff to proceed with design based upon the 2-story conceptual design at the December 12, 2017, Council Study Session.

    On May 23, 2017, Council authorized staff to pursue debt financing for a new Community Center. The project will construct a new two-story facility and will be phased such that the north wing of the facility (recreational area) will be demolished to allow space on the site for the new facility to be constructed, and allow the south wing (senior services area) of the building to remain open during construction. This phased method will require that some programs move to the Paul Derda Recreation Center while others would be suspended while the new facility is being constructed.

    At the end of August 2018, Staff and Citizens participated in "BCC Demo Day 2018" to say THANK YOU and GOODBYE to our beloved BCC.