Broomfield is getting a NEW Community Center!


The new facility is anticipated to the public open early October 2020. Details will be published soon!

Reconstruction of the Broomfield Community Center began in September 2018.

With such deep roots in the community, your input, feedback, thoughts and feelings about this project are paramount! Take a moment to share your fond memories, what you're excited about with a new facility and ask your questions using the tools below.


Use the Sign Up to Speak Up button on the right for monthly email updates and check out the project timeline and prior community feedback below that. Thank you for joining us on this exciting journey towards a newer, better community center!


Tell us what you think below! (You will need to sign up for a Broomfield Voice account)


The new facility is anticipated to the public open early October 2020. Details will be published soon!

Reconstruction of the Broomfield Community Center began in September 2018.

With such deep roots in the community, your input, feedback, thoughts and feelings about this project are paramount! Take a moment to share your fond memories, what you're excited about with a new facility and ask your questions using the tools below.


Use the Sign Up to Speak Up button on the right for monthly email updates and check out the project timeline and prior community feedback below that. Thank you for joining us on this exciting journey towards a newer, better community center!


Tell us what you think below! (You will need to sign up for a Broomfield Voice account)

  • September 2020 Update

    supporting image

    Site Work: In August, the sitework continued with completion of the Senior Center demolition, final lift of paving on the north lot section, and misc other site work. In September, the focus will be on landscaping and site furnishings on the north lot section as well as over-excavation, curb and gutter, and final paving of the south parking lot section to be complete with the final paving and parking lot striping of the south lot by the end of the month. In addition, the culvert replacement work at the west ditch crossing will be completed as well as the remaining underground water main loop connection near the intersection of W 3rd Ave and Spader. The remaining site work on the east side of the building will continue into October.

    Building: In August, the remaining millwork and pool systems were completed and only a few change order items remained for completion in September. Recreational Staff has occupied the building fully. In September the misc change order work to address final building inspection issues found and punch list work will continue through the end of the month to wrap up the final touches for the ribbon cutting on October 3rd and opening to the public on October 5th.

    It was realized in early September that the south parking lot section would not be complete enough to allow safe access for the public, so the project team decided to delay the opening by two weeks to October 5th. The remaining landscaping and hardscapes for the north-south trail connection along Brunner Reservoir are scheduled to be complete by the end of October. To view a timelapse photo collage of the building construction click HERE.

  • Check out the progress of the new BCC!

    24 September, 2019